Greiner Tackles Historic Bridge Removal
The first challenge was to get Greiner’s 600-ton Demag AC-500 with super lift and 75-ton Link Belt truck crane on the jobsite at the same time.
A landmark in Lenhartsville, PA, the old bridge spans Maiden Creek.
“The site was very tight,” said Dan Haulman, crane division manager for Greiner Industries. “The first challenge was to get our 600-ton Demag AC-500 with super lift and 75-ton Link Belt truck crane on the jobsite at the same time. The access road was very unlevel and created difficulty setting up both cranes.”
Super lift
The Greiner team rigged the Demag AC-500 all terrain crane with 352,000 pounds of counterweight. The Link-Belt 8675 was used to help rig the larger crane.
“Due to the length of rigging, 136 feet per leg, we needed to run all 183 feet of main boom,” Haulman said. “At a 75-foot lift radius, the super lift greatly increased the capacity of the crane. Basically the capacity went up from 87,000 pounds to 138,000 pounds.”
There was a concern that the old bridge wouldn’t stay intact throughout the lift, Haulman explained. Before the bridge was lifted by the crane, a house moving company came in and raised the bridge off its foundation. For further safety, bracings were used to strengthen the bridge structure.
“We knew the bridge would be completely free when we picked it,” Haulman said. “This added a tremendous safety factor as we then knew the bridge would not get hung up anywhere when lifting.”
Based in Mount Joy, PA, Greiner Industries’ Crane Division has a fleet of 11 cranes. The company acquired its Demag AC-500 to compete in the bridge market, Haulman said. Greiner purchased the crane from Empire Crane based in Syracuse, NY.
“We chose this crane because of its fantastic chart and the ease of setting the machine up in tight spaces,” Haulman said.
When restored, Greiner’s team will set new steel I-beams in place and install the re-engineered bridge back in place.